District's 4A Bond Shares Exciting Progress in March Miller, Impact, vestibules, ventilation systems, roofing, and summer projects galore ... the Bond folks have had an active month in March, and they are looking ahead to a very busy summer. Published March 31, 2023
Final Durango High School CIC/Impact Designs Jacobs Project Manager Devon Merriman and representatives from Anderson Mason Dale Architects presented the final Durango High School CIC/Impact designs to the Board of Education on October 25, 2022. Published November 8, 2022
Miller Middle School Bond Update October 2022 Jacobs Bond Project Manager Devon Merriman provided a presentation of the new Miller Middle School to the Durango School District 9-R Board of Education on Tuesday October 25, 2022. Published October 25, 2022
End of Summer 2022 Bond 4A Project Updates The Durango School District 9-R End of Summer 2022 4A Bond Project Updates were presented to the Durango School District 9-R Board of Educaiton on August 30, 2022 by Devon Merriman, Jacobs Program Manager Published September 21, 2022
Prepare For Impact! DHS Band Will Play At Groundbreaking Sept. 19 at Noon What is the best way to kick off a new building? With fanfare from the Durango High School Band! Students, staff and community members are welcome to celebrate a dream come true with a rousing mini-performance on Monday during the lunch hour at Durango High School, on Monday Sept. 19. Published September 16, 2022
Bond Oversight Committee Update - June 9, 2022 Currently 23% of the Bond funds have been committed, with abut 77% left.Local participation remains strong, with about 63% of funds allocated locally (74% when charter allocations are included). Published June 15, 2022
Schematic Design for IMPACT Career Center at DHS. At the May 24 Durango School District 9-R Board of Education Regular Meeting, representatives from Anderson Mason Dale Architects-including DHS student intern Nick Huber, Jaynes Corporation, and Jacobs Bond Project Management presented the IMPACT Career Center Schematic Design community update. Published May 25, 2022
New Miller Middle School Schematic Design At the April 26 Durango School District 9-R Board of Education Regular Meeting, Representatives from Cuningham Group, Bryan Construction and Reynolds Ash + Associates presented the Miller Middle School Schematic Design community update. Published April 29, 2022
LEADING EDGE for Transportation & Construction Business Program Get ready for Infrastructure Bill projects in 2022! Create a strategic plan for growth during this 9-week business planning program designed for consultants and contractors in the transportation construction industry. Course is April 12-June 14, 2022. Published April 7, 2022
Construction Market Escalations Impact Bond Projects At the March 29, 2022 9-R Board of Education Regular Meeting, Jacobs Bond Project Manager, Devon Merriman, presented an update on construction cost escalations that are impacting the Durango 9-R 4A Bond construction projects. Published March 30, 2022