District News » October 2026 bond update: Three Springs road progress, workforce housing expansion, and summer projects completed

October 2026 bond update: Three Springs road progress, workforce housing expansion, and summer projects completed

Funded by the 2024 Investing in Our Schools bond, these milestone projects ensure modern facilities and critical support for DSD educators and students.

Citizens' Bond Oversight Committee (CBOC)

The committee continues to meet monthly with the purpose of overseeing the process, validating that spending conforms to ballot language, and reviewing the budget.

Long-Range Planning Committee (LRPC)

The LRPC will begin meeting again in November 2026, continuing its focus on the district's long-term plans regarding school consolidation and replacement.

Three Springs Elementary School (TSES)

Work on the Wilson Gulch roadway and the school site itself continues to progress smoothly. The road surface will soon be poured, and curbs and sidewalks are already in place. Pouring this road will provide tremendous benefit by allowing more direct access to the construction site for the duration of the project. As for the school itself, all foundations are poured, and we are very close to seeing some vertical construction. 

Workforce Housing

The district's staff housing program currently sits at approximately 94% occupancy. In response to this demand, the Board of Education authorized expanding the program, and the district is under contract to purchase at least six townhomes to create both geographic and unit-type diversity in the district's workforce housing portfolio.  

Master Schedule

A copy of the master schedule will be included in all future updates. It is critical to note that with a program this large, things may change along the way. 

Fall 2025

  • Fleet replacements at Transportation (partially completed; will be ongoing through bond)
  • Technology replacements (partially completed; ongoing through bond)
  • Durango Big Picture High School renovations begin (completed)

Spring 2026

  • Low-flow water fixture scope (completed)

Summer 2026

  • Deferred maintenance scope at Needham Elementary School, Riverview Elementary School, Animas Valley Elementary School, and Florida Mesa Elementary School (completed)
  • Asphalt/concrete scope, districtwide (completed)
  • Roofing scope at Needham Elementary School and Riverview Elementary School (completed)
  • Furniture replacements — Phase 1 (completed)
  • Media center carpet replacement at Needham Elementary School, Animas Valley Elementary School, and Escalante Middle School (completed)
  • Facilities warehouse renovations (completed)
  • Wilson Gulch Drive improvements, related to Three Springs Elementary School (work ongoing)

Summer 2027

  • Deferred maintenance scope at Durango High School — Phase 1, Escalante Middle School, Fort Lewis Mesa Elementary School, and Transportation (scoping process continues)
  • The Hub renovations (scoping process continues)
  • Furniture replacements — Phase 2 (scoping process continues)
  • Escalante Middle School renovations/improvements scope — Phase 1 (scoping process underway)

Summer 2028

  • Deferred maintenance scope at Durango High School — Phase 2, Park Elementary School, and Sunnyside Elementary School
  • Escalante Middle School renovations/improvements scope — Phase 2 (if needed)
  • Florida Mesa Elementary School repurpose scope (TBD)
  • Furniture replacements — Phase 3 (TBD)
Published